Petition to Rescind Conditional Site-Plan Approval and Require Adherence to §410.010(G)
Proposed Asphalt Operation · 50 Roelker Road · Wright City, Missouri
Originally submitted July 20, 2026 · resubmitted July 30, 2026 · third submission, August 17, 2026 — filed with both the Board of Aldermen and the Planning & Zoning Commission
This petition remains open and pending. Current through August 17, 2026.
Proposed Asphalt Operation · 50 Roelker Road · Wright City, Missouri
The petitioners respectfully request that the Wright City Board of Aldermen rescind its June 11, 2026 conditional site-plan approval and require the application to proceed in the sequence established by §410.010(G) of the Wright City Code.
This petition is intentionally narrow. It does not ask the Board to approve or deny the proposed asphalt operation. It asks the Board to correct the procedural sequence so that the legal parcel configuration is established before a completed site plan is reviewed and approved.
Note on scope: the petitioners' primary focus here is the procedural validity of the June 11, 2026 approval and the request that the Board rescind and revote only after the proper §410.010(G) sequence is completed. Whether the proposed operation is properly classified as a permitted-by-right M-1 use is a separate and ongoing concern of the petitioners, but that classification question is properly directed to the Planning and Zoning Commission and the Zoning Enforcement Officer in the first instance (see Volume II). Nothing in this petition concedes, waives, or resolves that separate question.
On June 11, 2026, the Board approved the site plan subject to conditions. Those conditions required submission of an updated site plan and a boundary-adjustment plat before development or building permits could be issued. The approval also stated that the proposed Lots 1 through 5 were conceptual and were not created by the site-plan approval.
The petitioners do not contend that the Board took no action. The Board approved the site plan subject to conditions. The concern is that the approval occurred before completion of the boundary-adjustment process necessary to establish the legal parcel configuration upon which a completed site plan should be based.
Why does this matter? Approving a site plan based on a parcel configuration (Lots 1 through 5) that had not yet been legally established means the plan was reviewed against boundaries, setbacks, lot lines, and right-of-way dedications that did not legally exist yet. That creates exactly the downstream conflicts the record shows — the 100-foot versus 90-foot right-of-way discrepancy, "six parcels" versus "one" versus "five lots" in Conditions 2 and 4, and Condition 4 itself acknowledging that the lots were conceptual only. Approving in that sequence risks an approval resting on a foundation that could later be challenged, and forces the applicant to potentially redo site-plan work once the real boundaries are set.
Section 410.010(G), as amended by Ordinance No. 1108, establishes the process for adjusting adjoining parcels under common ownership: submission of a boundary-adjustment plat; review and recommendation by the Planning and Zoning Commission; approval by the Board of Aldermen through ordinance; and recording of the approved plat before the adjusted parcel configuration becomes effective.
The June 11 approval conditions confirm that this process had not been completed when the site plan was approved. Requiring Planning and Zoning Commission review first also ensures the proposed use and parcel configuration are checked for zoning compliance by the body with that expertise (see Volume II), and that the Board's ultimate approval is guided by the proper reviewing authority.
Since the June 11, 2026 vote, the plan for this site has changed and the Board has not revisited it. A civil site plan revised in July 2026 to reference new entrance locations now exists, and a final consolidation plat was produced to the petitioners on August 6, 2026. Neither was before the Board on June 11. The approval therefore rests on a superseded configuration, and the entrance design — the element bearing most directly on Roelker Road traffic and safety — is not the design the Board reviewed.
The following items are absent from the approved plan. The petitioners are raising each of them with the Planning & Zoning Commission today, and bring them to the Board because the Board’s June 11 approval rests on the same document:
The City’s own reviewer has also identified open items. The Building Inspector’s July 15, 2026 review of the final plat states that it “appears to comply with many of the requirements… but there are a few items that are either missing, unclear, or cannot be verified from the plat alone,” and raises whether the tract contains a regulated stream under Chapter 412, along with tax certification, an abstract of title, an unlabeled tract, and state-plane coordinates. Those items remain open.
The petitioners therefore ask the Board to treat its June 11 approval as resting on an incomplete and now superseded plan, and to rescind and revote only after a complete plan — showing the equipment above, with heights and surfacing — is before it.
If such authority exists, the petitioners respectfully request identification of the specific Code provision, ordinance, administrative determination, or other legal authority permitting those parcel-configuration requirements to be completed after site-plan approval.
The conditional approval did not establish the legal parcel configuration and did not itself create the proposed Lots 1 through 5. The Board's conditions instead required the applicant to complete the parcel-adjustment process and revise the site plan after approval. As a result, the administrative record reflects that:
Without completion of each step required by §410.010(G), no legal boundary adjustment exists. Until those steps are completed, the six existing parcels remain the only legally established parcel configuration.
As petitioners' counsel has observed: "If there is a boundary adjustment, there would need to be an ordinance, which approved the boundary adjustment, and that ordinance would have to be passed by the Board of Aldermen as outlined under §410.010(G)(3)." Counsel further noted that, based on this review, "it does not appear that the Board has been following the[se requirements], and there does not appear to be an official boundary adjustment approved in compliance with their ordinances."
This discrepancy is not merely theoretical. Verification of the Missouri DNR stormwater permit for this site shows that the permit was issued based on a five-lot site plan — the same conceptual Lots 1 through 5 that Condition 4 of the June 11 approval states were not legally created. The same appears true of the approved public water supply district (PWSD) water permit for this site, likewise issued based on the five-lot configuration (see Volume IV, Exhibits G, H, and I). The City is respectfully asked to reconcile how these state and utility-district permits could be issued against a five-lot configuration that, under the City's own approval conditions, does not yet legally exist.
Correcting the sequence would give the applicant, City officials, neighboring property owners, and the public a clear record of the legal parcel boundaries, the requirements applicable to those parcels, and the completed site plan considered by the Planning and Zoning Commission and Board of Aldermen. It also protects the landowner from unnecessary expense: if the applicable zoning review determines that the proposed use, parcel configuration, or site arrangement does not comply with applicable standards, the landowner should receive that determination early — before incurring substantial costs for final engineering, site-plan preparation, roadway design, and drainage plans.
The petitioners respectfully request that the Board of Aldermen:
The petitioners do not request that the Board predetermine whether the proposed asphalt operation should ultimately be approved or denied. They request only that the June 11, 2026 conditional site-plan approval be rescinded and that the application proceed in the proper order: boundary-adjustment review, approval, and recording first; completed site-plan review and approval second.
This corrective action would ensure adherence to §410.010(G) and allow any future decision to be made upon the legally established parcel configuration and a complete, accurate, and clearly documented administrative record.
Respectfully submitted,
The Petitioners
To avoid unnecessary duplication and the possibility of inconsistent versions, the following materials are submitted as separate shared volumes and are incorporated by reference into this petition:
Volume III — Shared Community Record (open volume)
Volume IV — Administrative Record and Supporting Documents (open volume)
These shared volumes are submitted once for use with both the Board of Aldermen petition (Volume I) and the Planning and Zoning Commission petition (Volume II). They should be preserved, filed, and distributed with each applicable petition as part of the complete submission.